Building a House in 7 Steps | Step 4: Permitting

Step 4 of the series: how we move a set of plans through permitting and keep the timeline honest.

Full guide: The 7 Steps

Step 4 of the seven step series. Permitting is the step people dread and the step that costs them the most time, and almost none of that time is the city’s fault. In the same jurisdiction where other people wait 6 to 12 months, we pull permits in 45 to 60 days. The difference is not a relationship. It is follow up.

Two parties actually matter

Your architect and your jurisdiction. That is the whole permitting relationship. If your builder is running the submittal for you, expect a markup on the architect, so keep direct contact with the architect yourself. The builder still matters here, because the energy code answers come from his side of the house.

What goes into a submittal package

  1. 01

    Plans plus engineering

    The architect draws the box, the structural engineer specifies what holds it up: 2x4 or 2x6 walls and the rest of the details. Some jurisdictions let you use prescriptive code, a set of pre-engineered rules, instead of hiring your own structural engineer.

  2. 02

    Site plan

    What the lot looks like and exactly where the house sits on it.

  3. 03

    Energy code sheet

    Square footage, the volume you are heating, furnace type, water heater type, gas or electric, window glazing, and insulation values such as R15 in a 2x4 wall or R21 in a 2x6. The city is checking that the system is neither undersized nor wasteful.

You do not need to know any of this personally. Your architect has submitted plans many times and carries a standard set of typical specifications. Your builder answers the energy code question, the storm facility, and erosion control. Ruben asked his architect what it would cost to handle the entire submittal on his fourth personal house: $500 to $1,000, depending on how many correction rounds it takes.

The correction loop, and where the months go

You submit through the city portal. The city gives you a target review date, usually 2 to 4 weeks out, and comes back with corrections: show the setback here, make the storm facility bigger, show where the roof water is collected and dispersed. You route structural corrections to the engineer, everything else to the architect, and resubmit. Most projects take one to three rounds. Your only job is to shrink the gap between rounds.

Master coordination, or adult babysitting

Here is the exact sequence that makes the difference. Ask the architect what day he is submitting. On that morning, confirm he submitted. Then email the permitting department directly and confirm they received it. Two answers are possible: yes we have it, or we do not know what you are talking about. The second answer is the one that saves you three months, because the alternative is finding out in month four that nobody ever hit send.

Once the city confirms receipt, ask them one more question: what is your target review date? Say the answer is the 21st. Go back to the architect and ask him to book the 22nd on his schedule now. Architects run 2 to 8 weeks out. If you wait until corrections land on the 21st to call him, you just added eight weeks to your project for no reason.

Trust but verify, at every handoff. The city can only review what was actually submitted, and an architect can only turn corrections around on a day he has reserved for you.

Ready to issue is the finish line that matters

After the last correction clears, the file moves to RTI, ready to issue, called preissuance in Portland. The city confirms every reviewer signed off, you pay permit fees, and you can break ground. Pay attention to this stage for one specific reason: an owner builder loan requires permits in ready to issue status before the loan can close.

Step 4: permitting

0/13

Ready to stop watching and start building?

Join the BuildUp Challenge and book a call with our team.

Join the BuildUp Challenge

Watch more on Arthur's channel.

Common questions

How long does it take to get building permits?

It depends on the jurisdiction and on your follow up. In markets where other people wait 6 to 12 months, we consistently pull permits in 45 to 60 days. The city gives a target review date usually 2 to 4 weeks after submittal, then most projects run one to three correction rounds.

What goes into a building permit submittal package?

Plans with structural engineering, a site plan showing where the house sits on the lot, and an energy code sheet covering square footage, furnace and water heater type, window glazing, and insulation values such as R15 in a 2x4 wall or R21 in a 2x6.

Do I need to understand energy code and structural engineering myself?

No. The architect coordinates with the structural engineer, and the builder answers energy code, storm facility, and erosion control. On his fourth personal house, Ruben's architect quoted $500 to $1,000 to handle the entire submittal, depending on how many correction rounds it takes.

How do I speed up the permitting process?

Verify every handoff. Get a submittal date from the architect, confirm that morning he actually submitted, then email the permitting department yourself to confirm they received it. Ask the city for its target review date and book the architect for the day after, because architects run 2 to 8 weeks out.

What does ready to issue mean?

RTI, called preissuance in Portland, is the stage after your last correction clears, where the city confirms every reviewer signed off. You then pay permit fees and can break ground. It matters for financing too: an owner builder loan requires permits in ready to issue status before it can close.

Nationwide

Where our clients are building.

65+ active member builds, 300+ units in progress, across 20+ states. Click a market to see who is building there.

346

Units developing live

49

Markets

Map of the United States showing where BuildUp clients are developing
See all developments

Your next step

Where are you right now?

New to development

Start with the BuildUp Challenge

A step-by-step challenge to line up your first deal, with our team beside you.

Join the Challenge

Live every week

Join the weekly live masterclass

Arthur and Ruben break down real deals and answer your questions in a live Q&A.

Join the live masterclass

Ready to build

Talk to our team

Development consulting for people ready to put a real deal together now.

Explore consulting